Boral Resources Deer Park Quarry 22kv Reticulation

Boral Deer Park Quarry image1

Key Facts

Project: Boral Resources Deer Park Quarry 22kv reticulation
Client: Boral Resources
Location: Deer Park, Victoria
Duration: 2016

In late 2015, Electrix was awarded the contract by Boral Resources Victoria to undertake the engineering, procurement and construction of the 22kV network infrastructure at the new Deer Park Quarry site.


The new Deer Park Quarry site will serve as the replacement to the existing quarry site, located directly across the road with production expected to commence in the third quarter 2017.

The design scope included;
• Maximum load calculations
• 22kV infrastructure design
• Transformer design
• Earthing design including step/touch potential calculations
• Protection study and circuit breaker setting calculations
• Arc flash incident energy analysis

The site work component of the scope can be described as the installation of the underground 22kV cable reticulation network between the property pole and adjacent SM6 Metering Station, the SM6 Switching Station and associated distribution Kiosk Transformers.

Electrix worked very closely with Boral Resources at all stages of the project forming a strong working relationship with the client and completed the works ahead of schedule.

 